Easthampton, MA

Easthampton, MA Accessory Dwelling Unit (ADU) Rules

City Acceptance Rating: 9/10

Last Updated: 11.21.2026

What You Need To Know

Easthampton was ahead of the curve. The city opened every zoning district to accessory apartments in 2021, well before Massachusetts made ADUs a protected use statewide on February 2, 2025. Today an ADU is a by-right use in every district in the city, and the state law fills in the rest: up to 900 sq ft or half the size of the main home, whichever is smaller, with no special permit and no owner-occupancy requirement.

Type of ADU Permit Required

A building permit from the Building Department. On our most recent Easthampton ADU there was no Zoning Board, Planning Board, Historical or Conservation review.

ADU Rules

  • Where: All zoning districts, on a lot with a single-family or two-family home.

  • How many: One ADU per lot.

  • Size: Up to 900 sq ft for a new detached ADU or a newly built attached one.

  • Parking: One off-street space for the ADU, built to match the existing driveway and connected to it. The Building Commissioner can waive it for a good reason given in writing, such as an occupant with a disability or one who does not own a car.

  • Driveway buffer: A new or widened driveway within 10 feet of a side or rear lot line needs a 6-foot landscaped buffer, unless you file a written agreement with the neighbor.

  • Design: The ADU should match the existing house. Attached and interior units keep the look of a single- or two-family home, with their own entrance. Stairs above the first floor go inside the building, or outside where they do not face the street.

  • Dimensional rules: Height, setbacks and building coverage for your district apply. An existing accessory building can be converted if its footprint and height stay the same.

  • Ownership: The house and the ADU stay under one ownership. No condo split.

  • Owner occupancy: Not required. State law removed this in 2025.

  • Short-term rentals: Easthampton defines a short-term rental as 28 consecutive days or fewer and requires registration with the city.

  • Taxes: A property with a second unit may be assessed as a two-family.

From Our Experience

We have completed five ADUs in Easthampton, in 2020, 2022, 2023, 2025 and 2026. They include a 526 sq ft one-bedroom, a 648 sq ft one-bedroom built where an above-ground pool used to be, and an 800 sq ft two-bedroom with cathedral ceilings and a deck.

  • Side yards and front yards can work. Our 2026 ADU is an accessible home in the side yard. We found no rule against placing an ADU in the front yard.

  • Plan on three small permits beyond the building permit. Our latest build needed a trench permit, a water service permit and a driveway permit.

  • Get a survey. A licensed survey was needed to lock in setbacks.

  • Drainage is light-touch. There is no formal stormwater requirement for a single ADU. The ordinance asks that roof and driveway runoff be routed through vegetated areas or infiltration where possible. We used a drywell.

Water. City water through the Easthampton Department of Public Works. Our 2026 ADU connected to the existing service inside the basement, after the meter, with no meter upgrade and no new street connection.

Sewer. City sewer. The ADU tied into the home's existing 4-inch line with no pump. We scoped the old cast-iron line first, and the scope recommended a hydro-cleaning before tying in, about $1,750. Scope yours early.

Sprinklers. Not required.

Fees we have seen (2026). Building permit: $7.50 per $1,000 of construction cost. Plumbing and electrical permits: about $400 together.